Proposed tungsten mine on Yukon-NWT border gets federal funding

An aerial view of Fireweed Zinc's Tom deposit, some 13 km from the Mactung property
An aerial view of Fireweed Zinc's Tom deposit, some 13 km from the Mactung property. Photo: Fireweed Zinc

Advertisement.

The federal government is investing up to $14 million in a proposed tungsten mine situated on the NWT-Yukon border.

Owner Fireweed Metals has not yet made a final investment decision on the Mactung mine.

The $14 million – made through the Global Partnerships Initiative, a federal critical minerals fund– aims to get the Vancouver-based company closer to a positive decision by supporting engineering, validation and technical work.

In a press release, Fireweed Metals CEO Ian Gibbs described the investment as encouraging, saying it recognized Mactung’s tungsten as a “cornerstone asset.”

Advertisement.

Advertisement.

That said, Gibbs added in a Tuesday phone interview with Cabin Radio, “there’s still an awful lot of work to be done before we can reach a final investment decision.”

A feasibility study is expected to wrap up in early 2027, followed by permitting processes.

“It will take some time for those licences to be evaluated and issued,” said Gibbs, “and only upon receipt of those licences would we be in a place to have a formal investment decision.”

Fireweed will look to reach that decision in 2028 or 2029, Gibbs said.

Advertisement.

Advertisement.

The project’s cost estimate will be fleshed out in the feasibility study but “we’re probably trending to a sub-billion dollar capital cost, which, in the grand scheme of mining these days, is quite manageable,” Gibbs said.

The proposed Mactung mine straddles the NWT-Yukon border in the Selwyn Mountains. It is located within the traditional territories of the Kaska Dena Nation and the First Nation of Na-cho Nyäk Dun, as well as in the Sahtu Settlement Area, Fireweed’s website notes.

The mine is situated right at the end of the North Canol Road, which is the northern portion of Yukon Highway Six. Fireweed is currently talking to the federal government and Yukon government about improving the road infrastructure, Gibbs said.

“We take rigs and fuel and people up and down that road,” he said, “but it wouldn’t be suitable in its current condition for the construction and operation of a mine.”

‘Deeply vulnerable supply chain’

In an emailed statement. the NWT government said it welcomed the federal funding commitment.

“The project has the opportunity to create northern jobs, attract investment, strengthen critical mineral supply chains, and reinforce the role of the North as a key contributor to Canada’s economic and strategic priorities,” that statement read.

The GNWT considers Mactung to be one of the world’s largest undeveloped high-grade tungsten deposits and a significant opportunity for both the Northwest Territories and Yukon.

Tungsten is a hard, dense metal with a high melting point. It is widely used in manufacturing for things like cutting tools, electronics, aerospace superalloys, semiconductors, defence and precision manufacturing.

Advertisement.

Advertisement.

Ian Ponsford, Fireweed’s vice-president of external affairs, emphasized that tungsten “is a deeply vulnerable supply chain in the West, generally.” 

China controls 83 percent of global tungsten production, according to the US Geological Survey.

“If we’re going to be able to have a manufacturing base, and a stable economy, and the ability to make things, we’re going to need a reliable supply of tungsten,” Ponsford said in an interview.

Opening Mactung – “one of the largest high-grade tungsten deposits on the planet” – would help address supply chain vulnerability, he said.

In 2024, Canada and the US Department of Defence committed C$12.9 million and US$15.8 million respectively to advance design, studies, baseline data collection and First Nations engagement for the North Canol Road, as well as transmission infrastructure needed for mine development and critical minerals projects in eastern Yukon. Canada’s $12.9 million came from the Critical Mineral Infrastructure Fund.

The latest $14 million is mostly about updating engineering work, Ponsford said, but also supports the company to look at downstream processing opportunities – how the rock is processed and shipped to customers.

Part of Fireweed’s feasibility study is looking at power generation options, including weighing the tradeoffs of using gas versus diesel. Ponsford said the feasibility study will also provide a better understanding of the project’s labour requirements. He currently anticipates a roughly 300-person workforce.

Small operation

The Mactung mine tungsten deposit was discovered in 1962, according to Fireweed Metals’ website.

Advertisement.

Advertisement.

A lot of groundwork has already been laid: a company called North American Tungsten Limited did a feasibility study in 2008 and 2009 and went through the Yukon’s environmental assessment process in 2014, CEO Gibbs said.

As far as mines go, he added, this one would be relatively small, operating at about 2,000 tonnes per day. It would be fly-in, fly-out. 

“The price [of tungsten] has been increasing quite dramatically,” Gibbs said. “The price that was used when they did the feasibility study in 2008 was $300 per MTU (metric ton unit), and the price recently has been well above that, almost nine times that price recently.

“While there will have been inflation to the cost since 2008, we’re confident that the increase in price will well offset the inflation of cost over that time.”

The price of tungsten increased sixfold between January 2025 and April 2026, according to the International Energy Agency’s 2026 Global Critical Minerals Outlook report. Multiple factors are at play, including increased demand and export controls imposed by China, the IEA noted.