Hay River’s town council has endorsed a delivery model for a new water treatment plant, moving the estimated $28.1-million project closer to its procurement stage.
During a Monday meeting, council endorsed progressive design-build as the preferred approach for the project and approved a preliminary financial plan incorporating a federal contribution, proposed third-party contributions, town reserves and borrowing.
The decision follows a November 9 council presentation from Deloitte LLP, which was hired by the town to assess different ways of delivering the project.
Deloitte recommended progressive design-build, a model that brings a design and construction team together earlier to develop the plans, costs and construction schedule collaboratively.
According to the business case presented to council, the approach would allow northern construction challenges – including transportation, material availability and seasonal construction windows – to be considered earlier in the process.
It would also allow council to review the proposed design and costs before deciding whether to proceed with construction.
Deloitte estimated the development phase could take 18 to 24 months.
The town’s economic development and communications manager, Genny Smith, said considerable work has taken place since a federal funding announcement in April committed about $20 million to the project.
In a written response to Cabin Radio, Smith said the town hired Deloitte to prepare the business case and has been addressing water licensing requirements with the Mackenzie Valley Land and Water Board and airport land lease matters with the GNWT.
Smith said the town is reviewing its Procurement Bylaw to address the recommended delivery model and ensure it complies with applicable legislation.
Funding still needs to be finalized
Deloitte’s business case estimated construction costs at $28.1 million.
Beyon the federal contribution through the Build Canada Strong Fund, the town’s preliminary funding plan suggests the remaining amount would come from $2.8 million in proposed third-party contributions, $2 million from town reserves and $3.2 million through loans.
Smith said the proposed $2.8 million in third-party contributions has not yet been secured.
The funding plan is subject to approval through the town’s 2027 capital budget, which is scheduled to be considered by council on December 14.
Smith said that, if approved, procurement readiness work would begin immediately. The town has not yet set a date for launching the competitive procurement process.
2030 remains planning target
The town continues to use 2030 as its target for the new plant to enter service, but Smith said it is a planning target rather than a firm completion commitment.
According to the town, the timeline will be refined through procurement and the development phase. The existing treatment plant would continue operating until the new facility is commissioned.
The new plant project does not include replacing Hay River’s approximately eight-kilometre water intake line.
Smith said the town is continuing to investigate and assess the existing intake. Its condition and whether it needs upgrades or replacement have not yet been determined.
The findings are expected to inform how the intake is integrated with the new facility and whether further planning or funding will be required.
The town says community communication will become increasingly important as the project moves into design and development.
Smith said dedicated public meetings have been discussed as opportunities for residents to learn about the project and provide input, but no dates have been confirmed.